Watershed Maintenance Work List for 2025-2026
This page is being created so landowners and citizens can see what maintenance work we are working on at each site.
-
Riser inspections (opening gates/closing gates) and cleaning toe drains took place on 7-18-25
-
Monitoring vegetation at all sites on 7-18-25
-
Fish Kill on Site 18a- pond turned over
-
Fence at Bear Creek completed
-
We are waiting on our results on our Dam Rehabilitation Reports for all five sites. Inspections were completed in 2024 at each location. NRCS is reviewing the draft reports.
-
We are working on getting bids for mowing, rodent control, fertilizing at each site. Watershed Boards will have a meeting in August to open bids.
-
We are working on trying to get some grant funding to install water gauges at the sites. There is a current bid package out to get prices for the equipment and installation.
-
Fall mowing is projected to take place August 19, 2025 to September 19, 2025, weather permitting
-
NRCS will complete a design in August or September at site 10D of the plunge basin- we are working on a future project to repair the plunge basin.
-
SCDES will make an inspection at all the site after the fall mowing is completed.
-
Fertilizing is projected to take place after the fall mowing but before November 17, 2025
-
Rodent control is projected to take place December 29, 2025 to February 13, 2026, weather permitting
-
Watershed Boards annual inspections will take place in February 2026 or March 2026